November 7, 2025
Multi-rooms Video Installation

A kitchen renovation is one of the most rewarding home improvement projects—but it also requires a good deal of planning, patience, and time. Homeowners often wonder how long the entire process will take when working with a professional contractor. While the timeline can vary depending on the project’s scope and complexity, understanding the typical phases can help you plan better and set realistic expectations.

Average Timeline for a Full Kitchen Renovation

Most standard kitchen renovations take between 6 to 12 weeks from demolition to final touches, assuming there are no major delays. However, this doesn’t include the planning and design phase, which can add several weeks or even months before the work begins.

Pre-Construction Phase: 2–6 Weeks

  • Consultation and Estimates: Initial meetings with the contractor to define the scope.

  • Design and Layout Planning: Working with designers to finalize floor plans, cabinetry, and material selections.

  • Permits and Approvals: Depending on your location, obtaining permits can take 1–3 weeks.

Demolition: 2–4 Days

Demolition usually happens quickly—contractors will remove old cabinets, countertops, appliances, and flooring in a few days. It’s noisy and dusty, but it sets the stage for new installations.

Plumbing and Electrical Work: 3–5 Days

Before any new cabinets or surfaces go in, plumbers and electricians handle rough-ins for sinks, lighting, and appliances. This stage must pass inspection before moving forward.

Flooring Installation: 2–4 Days

Flooring comes next, whether it’s tile, vinyl, hardwood, or laminate. This needs to be complete before cabinetry begins.

Cabinetry and Countertops: 2–3 Weeks

Installing cabinets takes 3–5 days, but countertops often require precise measurement after the cabinets are in place. Fabrication and installation of custom counters (such as stone or quartz) can take an additional 1–2 weeks.

During this stage, many homeowners select high-quality materials like comptoirs Entrepot Cuisine to ensure both beauty and durability in their kitchen’s most used surfaces.

Backsplash, Painting, and Finishing Touches: 1–2 Weeks

Once countertops are installed, contractors proceed with tiling the backsplash, finishing any painting, installing trim, and adding final touches like cabinet hardware and light fixtures.

Final Inspection and Clean-Up: 1–2 Days

Before handing over the completed kitchen, contractors perform a final walkthrough, test appliances, and address any remaining punch-list items. Professional cleaning ensures the space is move-in ready.

Factors That Influence Renovation Timelines

Custom vs. Pre-Made Components

Custom cabinetry or counters require more time for manufacturing and delivery. Delays can occur due to supplier backlogs or design adjustments.

Permits and Inspections

Cities and counties vary in how quickly they issue permits or perform inspections. Any required changes based on inspections can add days or even weeks to your timeline.

Change Orders

When homeowners make mid-project changes to materials, layout, or appliances, it can disrupt the schedule. Every alteration requires reevaluation of time, cost, and scope.

Contractor Availability

The contractor’s schedule also affects the timeline. Busy contractors may need more lead time to begin, while smaller firms may move faster but take longer with fewer crew members.

Conclusion

While the average kitchen renovation takes between 6 to 12 weeks once construction begins, the total timeline—including planning, permits, and decision-making—can stretch longer. Working with a professional contractor helps streamline the process, but flexibility is key. Clear communication, timely decisions, and realistic expectations will help ensure your kitchen transformation goes smoothly—and results in a space that meets your needs and enhances your home.